Site Programme and Informatiom.
This information will be updated on a daily basis as the work progresses.
Start date Monday August 4th 2008.
Completion date August 29th 2008.
Works will commence on the western side of the street between numbers 7 to 69 and will take 2 weeks to complete. The works will include the removal and renewal of the footway including some kerb and back edging replacement. Access to properties will be maintained at all times.
Works will take place on the eastern side of the street followimg on, commencing Monday 18th August between numbers 4 and 72 and will be completed Friday 29th 2008.
No works are planned during the weekends or on Bank Holiday Monday. Works will commence each day at 8.00am and finish at 4.00Ppm.
For more information phone 01905 722333.